MAITLAND PRIVATE HOSPITAL STAGE 6B & THEATRE 5 & 6 UPGRADE
MAITLAND – HUNTER REGION, NSW
Description
Hospital demolition, fitout and theatre refurbishment
Client
Healthe Care
Market
Health
More Information
$5.2M
2017
PROJECT VALUE
CONTRACT
COMPLETED
Design & Construct
PROJECT OVERVIEW
The upgrade works to Maitland Private Hospital involved construction in five (5) work zones within the existing working hospital and included the demolition and upgrade of two operating theatres to expand its size and update with the latest State-of the- Art theatre equipment.
Red Eye were engaged to expand the Hospital’s facilities which included:
SCOPE OF WORKS
Demolition & New Fitout including construction of:
-
Holding Bay – 2 Beds
-
Dirty & Clean Utility
-
Discharge Lounge
-
Stage 1 Recovery = 5 Beds
-
Stage 2 recovery = 8 Chairs
-
Entry Waiting Area incl. Reception and Lobby
-
Interview & Consulting Rooms
-
Sterile Store & General Store room
-
Staff Toilet & Change Facilities / Staff Amenities
-
Comms room
Operating Theatre – Demolition of existing theatre & upgrade construction of:
-
2 x New State-of the- Art Operating Theatre Rooms
-
Anaesthetic Bay x 2
-
Scrub Bay x 2
-
Equipment Room
KEY TRADES UTILISED
-
Demolition
-
Windows & Doors (Aluminium glazing)
-
Plastering & Light Steel Frames (Incl. Lead lining)
-
Electrical (High Voltage / Nurse Call / Emergency)
-
Fire Services (Wet & Dry)
-
Hydraulics
-
Architectural Joinery (Staff Base, Reception, Nurse Station, Administration, Staff Kitchen, Change Rooms, Recovery Bedheads)
-
Medical Gas
-
Mechanical
-
Landscaping
-
Painting